Construction Manager Ben Hott updated the Board of Education on Building Excellence construction at the first meeting of the new school year.
Longfellow Liberal Arts will have a Grand Opening/Ribbon Cutting Ceremony on July 29 at 4:30 p.m. Everyone is invited to attend. Eugene Field is adding final touches and will be ready for a Grand Opening in the next couple of weeks.
The New Academy, (currently located at the Primary Academy) new classroom addition has the exterior shell complete and windows are being installed. The administration area is near completion, and the media center and cafeteria are in beginning phases.
At the Rock Island Center for Math & Science, classroom addition walls are constructed and almost enclosed. Gymnasium walls are also up. Much progress has been made during the month of July.
Thomas Jefferson Elementary repurposed their kitchen into a cafeteria and expanded the north wall off of the gymnasium to accomodate the new eating area. Tiles are in the ceiling and the flooring will be going in this week. Most of the painting is complete. Project has been delayed slightly and will be complete early in the school year.
Interior work has been the focus this summer at Ridgewood Elementary. The media center and cafeteria will be ready mid-August.