Construction at Frances Willard Elementary continues with the focus areas being the front office reconstruction and the classroom and cafeteria addition. The parking lot is complete on the west side of the school near the front entrance and is in use by staff and visitors.
Denkmann Elementary front office construction will be complete in the next week or two. New features include a space for small instruction and secure front entry. The cafeteria construction on the south side of the building continues, the exterior walls are up and the roof will be in place by the end of August. Cafeteria is slated to be complete by December.
Ridgewood Elementary kept busy over the summer with the new cafeteria (complete) as well as expanding the front face of the building for the new media center and additional classrooms.